Transpower is undertaking two types of consultation on this project
The timetable for the Part F consultation is as follows:
| Stage | Item | Description | Timing |
|---|---|---|---|
| Stage 1 | Submission period | Submissions invited on Transpower’s initial approach, assumptions and options documentation | Late May - Mid June 2008 Completed |
| Approach, assumptions and options workshop | Facilitating review of Transpower’s proposed approach and assumptions | 6 June 2008 Completed |
|
| Stage 2 | Submission period | Submissions invited on Transpower’s application of the Grid Investment Test (GIT). View GIT Consultation documents. View submissions. | 29 October 2008 - 19 November 2008 |
| Investment Proposal | Submission of a Grid Upgrade Plan to the Commission | Mid December |
More information on times and venues will be provided in due course.
| Item | Description | Timing |
|---|---|---|
| Introduction and Options | Introduction to project and invitation to submit feedback on four transmission upgrade options. View documentation | 01 - 26 September (Completed) |
Preferred Option Update |
Update on project including selection of preferred option from an indicative application of the Grid Investment Test, and how community feedback was used. | 29 October 2008 |
| Submission period | Submissions invited on Transpower’s application of the Grid Investment Test (GIT) and workshop* - register to attend above. View GIT Consultation documents | 29 October - 19 November 2008 |
| Drop-in Centre Taupo Library Story Place |
Opportunity for interested people to learn more about the process to date and for the future. | 13 November 12pm-8pm 14 November 9.30am-1pm |
| Investment Proposal | Submission of a Grid Upgrade Plan to the Commission. | Mid December |
* Note this is a technical assessment of Transpower’s approach under Part F of the Electricity Governance Rules.