Upper South Island Grid Upgrade

Monthly Snapshot

Ref: UPSI-TRAN-DEV-01 
Investment Proposal to Commerce Commission Expected around 2012
Commerce Commission Approval Not yet proposed
Projected Commissioning Date 2017-30
Monthly Update  
March 2012 Project timeline slipped further. Consultation now expected end of April/early May.
February 2012 Delay in industry consultatin until late March/early April
December 2011/January 2012 Industry consultation on short list and application of investment test planned for late February.
November 2011 Preparing for industry consultation on approach and short-listing in first quarter of 2012.
October 2011 On track to submit an investment proposal in May 2012.
September 2011 Progressing according to schedule
August 2011 Submission published
July 2011 RFI submissions close
June 2011 Request for Information. Submissions close 29 July.