Overview

This district is affected by two of the three components of the project including the construction of 1 new transmission tower, and a new substation north of the existing substation at Whakamaru.

Landscape planting to help reduce the visual effect of the transmission line and substation will also be undertaken. We will be working closely with the local community to ensure that any disruption from our construction activity is kept to a minimum.

REGIONAL MAP

Regional Map

LATEST NEWS

News image.

CommunityCare Fund: Supporting communities

The CommunityCare Fund supports projects in communities affected by our assets.

News image.

Construction Newsletter Issue 2

Information on construction works planned in the next month on overhead lines, substations and underground cables.

News image.

North Island Grid Upgrade Fact Sheet

Designed to keep you informed about what has been happening with the project, timeline and more. Click the image above to read.

News image.

CommunityCare Fund launches waka

System Operations Manager, Dan Twigg officially helped to launch two waka ama in Mangakino north of Taupo.

1 of 4

PROJECT TIMELINE

01.02.2010
Construction at Pakuranga substation starts
01.02.2010
Construction of overhead line starts
01.02.2010
Excavation and trenching of cable route starts
01.10.2010
Construction at Brownhill/Whakamaru substations start
01.04.2011
Erection of 7 monopoles in Waipa starts
01.09.2011
Stringing of transmission lines starts
16.09.2011
Commissioning of line