Skip to Main navigationSkip to Content  
 
Transpower LogoGrid New Zealand Title Image
Banner Image

Overview

This district is affected by two of the three components of the project including the construction of 1 new transmission tower, and a new substation north of the existing substation at Whakamaru.

Landscape planting to help reduce the visual effect of the transmission line and substation will also be undertaken. We will be working closely with the local community to ensure that any disruption from our construction activity is kept to a minimum.

REGIONAL MAP

Regional Map

LATEST NEWS

News image.

North Island Grid Upgrade Fact Sheet

Designed to keep you informed about what has been happening with the project, timeline and more. Click the image above to read.

1 of 1

PROJECT TIMELINE

01.02.2010
Construction at Pakuranga substation starts
01.02.2010
Construction of overhead line starts
01.02.2010
Excavation and trenching of cable route starts
01.10.2010
Construction at Brownhill/Whakamaru substations start
01.04.2011
Erection of 7 monopoles in Waipa starts
01.09.2011
Stringing of transmission lines starts
16.09.2011
Commissioning of line