The construction team have installed the first circuit of the 220kV cables through Dunvegan Rise, Moyrus Crescent, Kilkenny Drive, Mulroy Place, Macnean Drive, Maghera Drive, Chapel Road, Armoy Drive, Aclare Place, Te Irirangi Drive, Guys Road Reserve through to Ti Rakau Drive.
We are continuing to backfill and reinstate through these areas. We are currently trenching and installing cable between Ti Rakau Drive and the Pakuranga Substation and also installing the second circuit cable within the existing underground tunnel which runs parallel to our trenchline.