Project Update

The image below is a snapshot of progress for our four main phases of work on the overhead transmission line

The image below is a snapshot of progress for our four main phases of work on the overhead transmission line:

  • access – preparing access tracks to tower sites including temporary tracks, fencing and vegetation
  • foundations – foundation piling, stub setting and concrete pouring
  • assembly – pre-assembly of tower parts and then sections are lifted into place
  • stringing – helicopters stringing wires through towers.