Overview

This district has the overhead transmission line component of the project and includes the construction of 99 new transmission towers. The construction work includes building access tracks and tower foundations; erecting the transmission towers and stringing the conductors (wires). The work will be undertaken over the next two construction summers.

Landscape planting to help reduce the visual effect of the transmission line will also be undertaken. We will be working closely with the local community to ensure that any disruption from our construction activity is kept to a minimum.

REGIONAL MAP

Regional Map

LATEST NEWS

News image.

CommunityCare Fund: Supporting communities

The CommunityCare Fund supports projects in communities affected by our assets.

News image.

Construction Newsletter Issue 2

Information on construction works planned in the next month on overhead lines, substations and underground cables.

News image.

North Island Grid Upgrade Fact Sheet

Designed to keep you informed about what has been happening with the project, timeline and more.

News image.

CommunityCare Fund launches waka

System Operations Manager, Dan Twigg officially helped to launch two waka ama in Mangakino north of Taupo.

1 of 4

PROJECT TIMELINE

01.05.2010
Construction starts
01.05.2010
Building access tracks
01.06.2010
Start of tower foundations
01.06.2010
Transmission tower erection and assembly
01.10.2010
Tower foundation work recommences
01.04.2010
Project ends