Overview

This district has all three components of the project including the construction of 33 new transmission towers, two new substations (Brownhill and Pakuranga) and four new underground cable circuits. The overhead transmission line connects to the new Brownhill Road substation. Four underground cable circuits will run from this new switching station - the first two circuits will connect to Pakuranga substation, and the second two circuits will connect to Otahuhu substation at a later date (around 2020 or later), as demand increases. We will be working closely with the local community to ensure that any disruption from our construction activity is kept to a minimum.

REGIONAL MAP

Regional Map

LATEST NEWS

News image.

Construction finishing for winter at Pakuranga substation

Over summer we have constructed the foundation area for the switchyard.

News image.

CommunityCare Fund: Supporting communities

The CommunityCare Fund supports projects in communities affected by our assets.

News image.

Construction Newsletter Issue 2

Information on construction works planned in the next month on overhead lines, substations and underground cables.

News image.

North Island Grid Upgrade Fact Sheet

Designed to keep you informed about what has been happening with the project, timeline and more.

News image.

CommunityCare Fund launches waka

System Operations Manager, Dan Twigg officially helped to launch two waka ama in Mangakino north of Taupo.

1 of 5

PROJECT TIMELINE

01.02.2010
Construction on Pakuranga substation starts
01.02.2010
Surveying underground cable route
01.04.2010
Excavation underground cable route
01.04.2010
Building tracks to tower sites
01.05.2010
Install buildings at Pakuranga substation
01.08.2010
Trenching starts on underground cable
01.10.2010
Substation platform work at Pakuranga starts
01.10.2010
Construction at Brownhill substation starts
01.04.2012
Project ends