National Auto Synchronisation Points Project

Consultation

Transpower has begun consultation on this project.  Refer to the table below for timings and activity.

Item Involves Timing
Request for Information and Assumptions, Approach and Options Detailing the need and requesting feedback to this and Transpower’s approach. 28 August to 30 September 2009
Submit Grid Upgrade Plan Requesting funding approval to proceed from the Electricity Commission* Submitted December