Banner Image

Penrose New Interconnecting Transformer

Overview

What we're doing

Penrose New Location (June 2009)

As part of the North Auckland and Northland (NAAN) Grid Upgrade, Transpower is installing a new 250 MVA interconnecting transformer at the Penrose substation.  The new transformer is required to meet load increases at Penrose following changes needed for other components of the NAAN project.

Why we're doing it

This project together with the other components of the NAAN project will provide sufficient capacity for the foreseeable future.

Project Timeline

01.01.2009
Electricity Commission Approval
01.04.2009
Design Solution
01.08.2009
Award Tenders
01.12.2009
Construction
01.03.2010
Commissioning

Tendering

Tendering for this project (if any) will be made through either the GETS or Transpower website. Register at both these sites to be notified of any open tender release.

View Transpower's procurement policy.

  • Project Reference:
    PEN-POW_TFR-DEV-01
  • Region:
    Backbone
  • Status:
    Completed
  • Cost Bracket:
    B "$5 - $10 million"
  • Timing:
    2010