| Ref: UPNI_REA_SUP_DEV_02 | |
| Investment Proposal to Electricity Commission | May 2010 |
| Electricity Commission Approval | August 2010 |
| Projected Commissioning Date | 2012 |
| Monthly Update | |
| December 2011/January 2012 | Design activities continues for both Statcom turnkey contracts. A design package has been awarded to Beca to carry out enabling works for scope outside of Siemens contract. |
| November 2011 | UNI DSI project re-scoped |
| September 2011 | A turn-key contract for Penrose and Marsden STATCOMs were awarded in September. Completion dates of May and August 2013 respectively. |
| August 2011 | No successful tenders for Demand Response RFP |
| July 2011 | Project progressing according to programme |
| June 2011 | Project progressing according to programme. |