Skip to Main navigationSkip to Content  
 
Transpower LogoGrid New Zealand Title Image
Banner Image

Upper North Island Reactive Support Project

Monthly Snapshot

Ref: UPNI_REA_SUP_DEV_02
Investment Proposal to Electricity Commission May 2010
Electricity Commission Approval August 2010
Projected Commissioning Date 2012
Monthly Update  
December 2011/January 2012 Design activities continues for both Statcom turnkey contracts. A design package has been awarded to Beca to carry out enabling works for scope outside of Siemens contract.
November 2011 UNI DSI project re-scoped
September 2011 A turn-key contract for Penrose and Marsden STATCOMs were awarded in September. Completion dates of May and August 2013 respectively.
August 2011 No successful tenders for Demand Response RFP
July 2011 Project progressing according to programme
June 2011 Project progressing according to programme.