Penrose to Albany Cross Harbour Cables

Overview

What we're doing

Trench with pipes.

As part of its North Auckland and Northland (NAaN) Project, Transpower is installing an underground 220 kV cable connection between Penrose and Albany (via the Harbour Bridge), to provide more security to North Auckland and Northland.

This will provide an alternate electricity supply route to North Auckland and Northland, which presently relies on just one high capacity line between Otahuhu and Henderson for most of its power needs.

Why we're doing it

This is a long term solution providing sufficient capacity for the foreseeable future.

Project Timeline

01.05.2009
Electricity Commission Approval
01.01.2010
Design Solution
01.01.2011
Award Tenders
01.01.2012
Construction
01.01.2014
Commissioning

Tendering

Tendering for this project (if any) will be made through either the GETS or Transpower website. Register at both these sites to be notified of any open tender release.

  • Project Reference:
    ALB_PEN TRAN DEV-01
  • Region:
    Backbone
  • Status:
    Committed
  • Cost Bracket:
    G "$300 million plus"
  • Timing:
    2014
Large image of the Project Area show key close Close Icon print map Map Key