| Ref: LWTK_TRAN_DEV_01 | |
|---|---|
| Investment Proposal to Commerce Commission | Not yet proposed |
| Commerce Commission Approval | Not yet proposed |
| Projected Commissioning Date | 2012 |
| Monthly Update | |
| December 2011/January 2012 | Project effectively on hold. |
| November 2011 | Preparing for update to landowners and stakeholders in early December. |
| October 2011 | Project progressing according to programme schedule |
| September 2011 | Project progressing according to programme schedule |
| August 2011 | Project progressing according to programme schedule |
| July 2011 | Project progressing according to programme schedule |
| June 2011 | Work continues on possible interim solutions |