Kaitimako Transmission Reinforcement

Monthly Snapshot

Image Gallery

KMO-TRK-TRAN-EHMT-01 
Investment Proposal to Electricity Commission November 2009
Electricity Commission Approval 18 December 2009
Projected Commissioning Date October 2011
Monthly Update  
December 2011/January 2012 Construction contract awarded to Electrix. Contractor start up meeting held January 2012.
November 2011 Installation tenders for main substation works received and are under evaluation. Lack of Transpower approved drawings for primary equipment at this stage may lead to later project delay.
October 2011 Circuit commissioned late October.  Installation tender specification for the main substation works has been completed and the tenders issued.
September 2011 Preparing for final circuit commissioning in October
August 2011 Project progressing according to programme
July 2011 Planning outage works for October outages