Otahuhu Substation Diversity

Monthly Snapshot

Image Gallery

Monthly Update

Ref: OTA SUBEST DEV 01 
Investment Proposal to Electricity Commission December 2006
Electricity Commission Approval August 2007
Projected Commissioning Date June 2010
Monthly Update  
August 2010 Commissioning ceremony 19 August. Substation now fully commissioned.
July 2010 Site area completion works continue
June 2010 Cutover of remaining circuits (from OTC and SWN) timed for spring
May 2010 Incoming and outgoing circuits now transferred to GIS
Apr 2010 GIS/AIS substation commissioned successfully 7 April.  The rest of the project is planned to be substantially commissioned by the end of June
Mar 2010 Commissioning of the GIS facility commences 6 April
Feb 2010 Commissioning planning has begun
Jan 2010 Physical works diminishing as project nears commissioning phase
Nov 2009 Commencement of commissioning slipped until April 2010
Oct 2009 Work continuing on GIS installation and EHV cable troughs