| Ref: OTA SUBEST DEV 01 | |
|---|---|
| Investment Proposal to Electricity Commission | December 2006 |
| Electricity Commission Approval | August 2007 |
| Projected Commissioning Date | June 2010 |
| Monthly Update | |
| August 2010 | Commissioning ceremony 19 August. Substation now fully commissioned. |
| July 2010 | Site area completion works continue |
| June 2010 | Cutover of remaining circuits (from OTC and SWN) timed for spring |
| May 2010 | Incoming and outgoing circuits now transferred to GIS |
| Apr 2010 | GIS/AIS substation commissioned successfully 7 April. The rest of the project is planned to be substantially commissioned by the end of June |
| Mar 2010 | Commissioning of the GIS facility commences 6 April |
| Feb 2010 | Commissioning planning has begun |
| Jan 2010 | Physical works diminishing as project nears commissioning phase |
| Nov 2009 | Commencement of commissioning slipped until April 2010 |
| Oct 2009 | Work continuing on GIS installation and EHV cable troughs |