|
Ref: MDN-BUSC-DEV-01 |
|
| Investment Proposal to Electricity Commission | 29 May 2009 |
| Electricity Commission Approval | 3 July 2009 |
| Projected Commissioning Date | 11 February 2011 |
| Monthly Update | |
| July 2010 | Phase 2 installation contract was awarded at the end of July |
| June 2010 | T6 commissioned. Project now moving to phase 2 |
| May 2010 | All major commissionings complete apart from T6 |
| Apr 2010 | New bus to be commissioned in May. Control building 95% complete |
| Mar 2010 | Completed works for T5 and T6 220 kV connection bays. Completed 110 kV tie line pole installation |
| Feb 2010 | Completed majority of control building superstructure. Completed civil works for T5 and T6 220 kV connection bays |
| Jan 2010 | Site works started in December, control building foundations complete |
| Nov 2009 | Awarded main installation contract for project awarded |
| Oct 2009 | Site works due to start in November |