Marsden Substation Upgrade

Monthly Snapshot

Image Gallery

Monthly Update

Ref:  MDN-BUSC-DEV-01

 
Investment Proposal to Electricity Commission 29 May 2009
Electricity Commission Approval 3 July 2009
Projected Commissioning Date 11 February 2011
Monthly Update  
July 2010 Phase 2 installation contract was awarded at the end of July
June 2010 T6 commissioned. Project now moving to phase 2
May 2010 All major commissionings complete apart from T6
Apr 2010 New bus to be commissioned in May. Control building 95% complete
Mar 2010 Completed works for T5 and T6 220 kV connection bays. Completed 110 kV tie line pole installation
Feb 2010 Completed majority of control building superstructure.  Completed civil works for T5 and T6 220 kV connection bays
Jan 2010 Site works started in December, control building foundations complete
Nov 2009 Awarded main installation contract for project awarded
Oct 2009 Site works due to start in November