| Ref: LWSI-TRAN-EHMT-01 | |
|---|---|
| Investment Proposal to Electricity Commission | May 2010 |
| Electricity Commission Approval | September 2010 |
| Projected Commissioning Date | 2011-2016 |
| Monthly Update | |
| December 2011/January 2012 | Finalising route report. Conceptual design for Gore interconnecting transformers underway. Balclutha capacitors deferred to 2014-15. Invercargill transformer design to begin mid 2012. Detailed design of Roxburgh transformer nearly complete. |
| November 2011 | Continuing work on preferred route and structure type. |
| October 2011 | Continuing work on preferred route and structure type |
| September 2011 | Continuing work on preferred route and structure type |
| August 2011 | Working to have a preferred route and structure type by late September |
| July 2011 | Project progressing according to schedule |
| June 2011 | Continuing to discuss options with affected landowners. |