Skip to Main navigationSkip to Content  
 
Transpower LogoGrid New Zealand Title Image
Banner Image

Lower Waitaki Reliability

Monthly Snapshot

Ref: LWTK_TRAN_DEV_01 
Investment Proposal to Commerce Commission Not yet proposed
Commerce Commission Approval Not yet proposed
Projected Commissioning Date 2012
Monthly Update
November 2011 Preparing for update to landowners and stakeholders in early December.
October 2011 Project progressing according to programme schedule
September 2011 Project progressing according to programme schedule
August 2011 Project progressing according to programme schedule
July 2011 Project progressing according to programme schedule
June 2011 Work continues on possible interim solutions
March 2011 Updated stakeholders on progress: new line best long term option but only if load gows.
February 2011 Continuing work on refining costs of options
December 2010 / January 2011 Consultation period closed. Responses being considered