Skip to Main navigationSkip to Content  
 
Transpower LogoGrid New Zealand Title Image
Banner Image

Kaitimako Transmission Reinforcement

Monthly Snapshot

Image Gallery

KMO-TRK-TRAN-EHMT-01 
Investment Proposal to Electricity Commission November 2009
Electricity Commission Approval 18 December 2009
Projected Commissioning Date October 2011
Monthly Update  
November 2011 Installation tenders for main substation works received and are under evaluation. Lack of Transpower approved drawings for primary equipment at this stage may lead to later project delay.
October 2011 Circuit commissioned late October.  Installation tender specification for the main substation works has been completed and the tenders issued.
September 2011 Preparing for final circuit commissioning in October
August 2011 Project progressing according to programme
July 2011 Planning outage works for October outages
June 2011 The two KMO_TRK_1 & 2 circuits will be uprated to the new rating (80’C) on the 3rd of July 2011 with the remaining re-insulation works being completed by the end of October 2011
May 2011 Completed all remaining vegetation work.
April 2011 Completed all earthworks.  Arranged new commissioning outage for 2nd and 3rd July as earlier outage dates (April/May) not available.
March 2011 Completed two further outage programs to date. Completed the first lot of earthworks sites i.e. span 4-5, 4 sites to go.
February 2011 All landowners contacted before Xmas advising of work.  Expecting to get underway in March
December 2010 / January 2011 Main works contract has been awarded to Transfield Services