| Ref: ISL-RPC-DEV-01 | |
|---|---|
| Investment Proposal to Electricity Commission | June 2007 |
| Electricity Commission Approval | August 2007 |
| Projected Commissioning Date | November 2011 |
| Monthly Update | |
| November 2011 | RPC commissioned 9 November. Continuing with in-service monitoring for undefined period to ensure unit works as expected. |
| October 2011 | Commissioning tests underway |
| September 2011 | Issues resolved. Expecting to commission in early November. |
| August 2011 | Testing 75% completed. A voltage issue during testing caused by an error in the software of the local RPC is presently being investigated. Commissioning now expected to be complete in September. |
| July 2011 | Project continuing to progress to plan |
| June 2011 | Project continuing to progress to plan. |
| May 2011 | It is expected that the system commissioning tests will take up to four weeks to complete, depending on system conditions with the trial period starting in early August. |
| February 2011 | Christchurch earthquake has delayed commissioning now until approximately June 2011 |
| December 2010 / January 2011 | Installation has commenced. |