Islington Upgraded Reactive Power Controller

Monthly Snapshot

Image Gallery

Monthly Update

Ref: ISL-RPC-DEV-01 
Investment Proposal to Electricity Commission June 2007
Electricity Commission Approval August 2007
Projected Commissioning Date November 2011
Monthly Update  
November 2011 RPC commissioned 9 November. Continuing with in-service monitoring for undefined period to ensure unit works as expected.
October 2011 Commissioning tests underway
September 2011 Issues resolved. Expecting to commission in early November.
August 2011 Testing 75% completed.  A voltage issue during testing caused by an error in the software of the local RPC is presently being investigated.  Commissioning now expected to be complete in September.
July 2011 Project continuing to progress to plan
June 2011 Project continuing to progress to plan.
May 2011 It is expected that the system commissioning tests will take up to four weeks to complete, depending on system conditions with the trial period starting in early August.
February 2011 Christchurch earthquake has delayed commissioning now until approximately June 2011
December 2010 / January 2011 Installation has commenced.