| Ref: SFD_WNG-TRAN-EHMT-01 |
| Investment Proposal to Electricity Commission |
September 2009
|
| Electricity Commission Approval |
November 2009 |
| Projected Commissioning Date |
Winter 2012 |
| Monthly Update |
|
| March 2012 |
Stringing continuing |
| February 2012 |
Approximately 50% of the poles requiring replacement have been completed and stringing has commenced. |
| December 2011/January 2012 |
Live line work for Hawera to Waverley commencing 7 February. Outage works commencing 20 February. |
| November 2011 |
The outage for reconductoring the Hawera to Waverley section is scheduled to start in February 2012. Some poles and crossarms are planned to be replaced live line prior to the outage. |
| October 2011 |
Detailed design complete. Tender documents compiled. |
| September 2011 |
Detailed desing almost complete. Tender documents expected to be issued in October. |
| August 2011 |
Project progressing to programme schedule |